HKA Global Inc. · ~$5M construction delay claim
Construction Delay Claim Analysis
- Prepared and maintained document and schedule registers, organizing and reviewing 29 project schedules alongside change documentation, meeting minutes and contemporaneous project records.
- Extracted and validated schedule-related data from 40+ weekly foremen meeting minutes and multi-year project records to develop as-built activity timelines, track floor-by-floor progress and identify key construction milestones.
- Reviewed 29 Microsoft Project schedules for critical path activities, logic relationships, progress updates and scheduling inconsistencies, supporting forensic delay analysis and comparison of planned versus actual construction performance.